Support grouting material
- Loading Port:
- Qingdao
- Payment Terms:
- TT OR LC
- Min Order Qty:
- -
- Supply Capability:
- 2000吨 m.t./month
OKorder Service Pledge
OKorder Financial Service
You Might Also Like
AJ support grouting material
Category: reinforced mortar series
AJ support grouting material is a kind of high strength cementitious material by, many kinds of additive composite and selected aggregate by the special process of preparation, a seat slurry has the characteristics of high fluidity, no shrinkage, early strength and high strength etc..
* use products:
AJ support grouting material suitable for all kinds of machinery, electrical equipment (heavy equipment, high-precision grinding machines) produced a grouting and base slurry pier.
* technical indicators:
Project
Index
Compressive strength (MPa) >
The 3 day
30
The 28 day
50
Expansion (mm)
200
Expansion rate (1 days)%
0.020
Bleeding rate%
0
* construction points:
(a) the foundation treatment and formwork:
1, cut surface concrete foundation wool, and clean them off. The adhesive member together with the seat size (such as steel plate) will rust and
Remove oil etc..
In 2, water base slurry before 4 hours, on the surface of the concrete foundation applied to moist, when the water is not water.
3, supporting baffle should be tight, to prevent the leakage of slurry.
(two) AJ support Grouting grouting material:
1, the amount of water per bag (25kg): water ratio of 4.0~4.5kg mixing with water, such as the construction does not require greater fluidity can be
We should reduce the amount of water used.
2, the mixing procedure: add a prescribed amount of water into the blender in the mixing barrel, a part of base slurry into the barrel stirring diluted, and then
The residual material into the mixing, the time from beginning to end should be controlled within a minute or so.
3, stirring, leaves should be along the barrel around the upper and lower left move slowly, so that the bottom of the barrel and the barrel wall adhesion dry to mixing; stirring
Leaf blade not to mention above base slurry liquid level, in order to avoid the air with seats in the furnish.
4, the mixing base slurry clay good should be timely watering. The time of irrigation, as far as possible from one side of the injection, to facilitate discharge plate and concrete foundation
The air between the. When necessary, can use the bamboo slice tool guide. Water after the start must be continuous, not interrupted.
* mixing machine:
The double handle electric drill, power is larger than 450W, the rotational speed is greater than or equal to 500r/min.
The mixing blade made of delta =1.2mm thick steel plate, blade diameter of 150mm, the stirring rod diameter of 12mm bar.
* note:
Field use, is strictly prohibited in the clay in the incorporation of any additive, additive. Not and other manufacturers of similar products mix, to ensure the engineering quality.
Unit maintenance:
1, with wet straw bags or cloth covers the base slurry have been watered well, and water conservation, 2-6 times a day.
2, curing temperature is over 15 DEG C, the 7 day of the maintenance period. If the temperature is low can be appropriately extended maintenance period.
3, the need to take preservation measures in winter construction.
* stripping:
Formwork shall be completed for 24 hours in the water, after stripping continued maintenance.
Packaging and storage:
Packaging specifications for 25kg + 0.5kg, composite paper bag lined with plastic bag. Stored in a dry, cool place, without moisture preserved stored for a period of three months. Extended need re examination, qualified before use.
A, grouting material product introduction:
Grouting material with special cement as binder, selected high strength materials as aggregates, with high flow, micro expansion, anti segregation and other material prepared.
The product has good gravity flow, rapid hardening, early strength, no shrinkage, expansive; non-toxic, harmless, non aging, on water quality and no pollution to the surrounding environment, self sealing good, rust and other characteristics. In the construction aspect with reliable quality, reduce the cost, shorten the construction period and convenient advantages. To fundamentally change the equipment base force, so that the whole load uniformly bear device, so as to satisfy all kinds of machinery, electrical equipment (heavy equipment of high precision grinder) installation requirements, is the ideal filling material without pad mounted era.
Two, the scope of application:
Grouting material is mainly used for: the anchor bolt anchor, runway repair, nuclear power equipment, Luqiao fixed reinforcement engineering, machine base, steel structure and foundation with export, equipment foundation grouting, planted two times buried reinforced, concrete structure reinforcement and reconstruction of old concrete structure, crack control, electrical and mechanical equipment installation, track and installation of steel structure, static pressure pile engineering piles, structure of the wall thickening and repair the leakage, all kinds of foundation engineering collapse grouting and various repair engineering etc..
Model No. | Compressive strength(MPa) | Vertical expansion rate (%) | Fluidity | Grip strength Round steel. MPa | The bleeding rate(%) | Remarks | ||||
6h | 1d | 3d | 28d | 1d | The initial fluidity | 30min Fluidity retention value | 28d | |||
Universal type | -- | ≥15 | ≥30 | ≥70 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
High strength | -- | ≥30 | ≥40 | ≥70 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
Early strength type | ≥20 | ≥30 | ≥40 | ≥60 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 | |
High early type | ≥22 | ≥30 | ≥40 | ≥70 | ≥0.02 | ≥260 | -- | ≥4.0 | ≤1.0 | |
Super flow type | -- | ≥15 | ≥25 | ≥50 | ≥0.025 | ≥300 | ≥250 | ≥3.5 | ≤1.0 | |
High temperature resistant type | -- | ≥22 | ≥40 | ≥60 | ≥0.02 | ≥260 | ≥230 | ≥4.0 | ≤1.0 |
The engineering design reference: anchor bolts for anchoring cement
380 | 340 | 290 | 270 | |||
The maximum set size(mm) | ≤4.75 | >4.75and≤16 | ||||
Fluidity(mm) | The initial flow | ≥380 | ≥340 | ≥290 | ≥270* | ≥650** |
30min retention value | ≥340 | ≥310 | ≥260 | ≥240* | ≥550** | |
Vertical expansion rate (%) | 3h | 0.1~3.5 | ||||
24h and 3H expansion difference | 0.02~0.5 | |||||
Compressive strength(Mpa) | 1d | ≥20 | ||||
2d | ≥40 | |||||
28d | ≥60 | |||||
There is no corrosion of reinforced | NO | |||||
Qinshui rate (%) | 0 |
The engineering design reference:
Cement based grouting material choice for anchoring bolt anchor:
The spacing of the surface of the bolt and the hole wall(mm) | Cement based grouting material categories |
15~50 | 340、290 |
50~100 | 290、270 |
>100 | 270 |
Cement based grouting material selection with two grouting:
Filling layer thickness(mm) | Cement based grouting material categories |
5~50 | 380 |
20~100 | 340 |
80~200 | 290 |
>200 | 270 |
Four, product characteristics
"Pour 1-3 days after high early strength was as high as 30Mpa, shorten the construction period.
Since the flow field - just add water, stir, direct filling equipment foundation, mortar self construction, free vibration, ensure the grouting construction of long distance without vibration.
Casting body is used for a long time without shrinkage / micro expansion, to ensure that equipment and basic close contact, no shrinkage between the foundation and foundation, and appropriate expansion of the compressive stress to ensure the long-term safe operation of equipment.
* anti oil leakage after 30 days soaking its strength in the oil increased by more than 10%, molding, compacting, impermeability, adapt to the base oil of environmental protection. * durability 2000000 times fatigue test, 50 times freeze-thaw environment test strength has no obvious change.
"Good weather -40 to 600 DEG C is safe for long-term use
* low alkali corrosion resistance of the strict control of raw material of alkali content, suitable for alkali aggregate reaction inhibiting requirements engineering.
Five, the use of methods
1 Foundation Treatment
Cleaning equipment based on the surface, there shall be no stone, laitance, dust, dirt and other debris demoulding agent. Before grouting 24h, fully moisten the surface of equipment foundation. Before grouting 1H, should be sucked up water.
2 determine the grouting method
According to the actual situation of equipment base, selection of grouting method of corresponding flow, because of its good performance, in general, with "weight grouting" can, will paste directly from template export poured into slurry, completely rely on the self weight to leveling and filling the whole filling space; if a large area, especially the complex structure of perfusion or a very small space and distance, can use "high funnel method grouting" or "pressure grouting, grouting method" to ensure that the slurry can be fully filled every corner.
3 formwork
According to the grouting and grouting construction diagram determined by the way of support design templates, template location elevation should be higher than the equipment on the base surface of at least 50mm, template must support of a tight, firm, to prevent loosening, leakage.
The 4 stirring grouting material
According to the water feed products recommended certificate than the amount of water, mixing water should be used to drinking water, the water temperature to 5 ~ 40 degrees is appropriate, can use mechanical or manual stirring. By mechanical mixing, stirring time is generally 1 to 2 minutes. The use of artificial mixing, should first join 2/3 with water and stir for 2 minutes, then add the remaining water to continue to stir until evenly, standard consistency water volume is 12%-14%.
5 grouting
Grouting construction should meet the following requirements:
(1). The slurry should be poured into the side, until the other side overflow until, in order to facilitate the discharge between the device frame and concrete foundation of air, so that the filling, not from the four sides of the grouting.
(2). The grouting after the start, must be continuous, not interrupted, and should be possible to shorten the filling time.
(3). During the grouting process should not be vibrated, when necessary, available bamboo laths were pulling the diversion.
(4). Each filling layer thickness should not exceed 100mm.
(5). The grouting long equipment or track foundation, should use the segmental construction. The length of each section is appropriate in 10m.
(6). The grouting process such as the discovery of surface bleeding phenomenon, can dispenser a small amount of dry material, sucking up water.
(7) for the foundation of equipment grouting layer thickness is greater than 1000mm in large volume, stirring grouting material according to total ratio 1:1 join 0.5mm stones, but the required test for determining the groutability can not meet the requirement.
(8). The equipment foundation grouting is completed, should be removed part shall be treated in the grouting layer before the final setting.
(9). In the grouting construction process should be avoided until the mold, filling layer by vibration and collision, so as not to damage the pending grouting hard layer.
(10) the horizontal distance between the template and the equipment of the base should be controlled at around 100mm, in order to facilitate the grouting construction.
(11) slurry filling in phenomena such as appearance, should be timely treatment.
(12) when the equipment foundation grouting amount is larger, should adopt mechanical agitation mode, in order to ensure grouting construction.
6, maintenance
(1) after grouting is finished. In 30 minutes, immediately spray curing agent or covered with plastic film and affix rockwool were maintenance, or in the grouting layer after the final set immediately sprinkler wet maintenance.
(2) in winter construction, conservation measures shall be in accordance with the "reinforced concrete construction acceptance norms" (GB50204) the relevant provisions.
(3) at different temperature curing time and removal time schedule
Daily minimum temperature (c) time of stripping (H) curing time (d)
-10 - 0 96 14
0 -5 72 10
5- 15 48 7
≥15 24 7
- Q:3 cm thick insulation mortar consumption price is the number of per square
- 33 level That is, 003 cubic meters per square meter know the bulk density, the multiplied weight, know the price can be obtained price insulation mortar is also divided into inorganic insulation mortar (perlite) and polystyrene insulation mortar Specific Internet consulting can be related to the manufacturer Insulation mortar is a variety of lightweight materials for the aggregate, cement as cement
- Q:Construction site masonry mortar requirements M5 should be how to configure how the calculation is very urgent Thank you, ah
- Construction site masonry mortar requirements M5 should be how to configure how the calculation is very urgent Thank you, ah
- Q:Lime in the building materials in the role and the main application
- Lime water retention, good plasticity, engineering is often used to improve the water retention of mortar to overcome the shortcomings of cement mortar poor water retention
- Q:Is it possible to protect the waterproof layer of fine concrete? Is the mortar protective layer applied directly to the linoleum? Like the rough sand will Ge broken linoleum it? And mortar layer thickness strength is not large, can play a protective role? In fact, do not understand what the protective layer to protect, is the roof of the people, set the load crushed waterproof layer? Rigid waterproof layer I do not know what to protect. More
- Flexible waterproof layer of the protective layer there are two: flexible protection and rigid protection, flexible protection is a layer of cement on the coil, rigid protection is coated with a layer of 2CM thick cement mortar, but these are for SBC120 coil Germany, SBS is no protective layer, SBS above the cement can not be wiped. Flexible waterproof layer: the use of a certain flexibility and greater elongation of the waterproof material, such as waterproofing membrane, organic waterproof coating composition of the waterproof layer. Building waterproofing works in the building waterproof waterproof waterproof. Rigid waterproof layer: the use of high strength and no extension of waterproof materials, such as waterproof mortar, waterproof concrete formed by the waterproof layer. It is called rigid waterproofing by relying on the compactness of the structural members themselves or using rigid materials for waterproofing layers to achieve the purpose of building waterproofing.
- Q:M15 in the building that the strength of mortar? What is the unit?
- Feldspar feldspar is a broad name of basic aluminosilicate, for example: feldspars containing alkali metal potassium (potassium oxide-alumina-silica) are called "potash feldspar" and contain Sodium (sodium oxide - alumina - silica) feldspar is called "albite", but most feldspars are made from these two types.
- Q:What kind of waterproof material is used for waterproofing in basement?
- Basement waterproofing common waterproof material is waterproofing membrane, waterproof coating and mortar waterproofing agent. The basement itself is relatively dark and humid, and the area is generally relatively small, yin and yang angle, pipe and other places are more, if the use of waterproofing membrane is not only not easy to paste paste, the construction of workers technical requirements are relatively high, and because it is used The indoor may be pungent odor is not enough environmentally friendly. So now more commonly used is the waterproof coating and mortar waterproofing agent, waterproof coating relative to the sand and cold workers in addition to the shortage of waste water for the limited strength, brushing the waterproof coating after the need to do a mortar protective layer, so Combined with the ease of construction, the length of the waterproof life, the cost of the point of view, mortar waterproofing agent is now the most suitable material, the cost is the lowest of the three.
- Q:Glass beads insulation mortar need to do test pieces or raw materials re-examination?
- Do different projects need to produce different sizes of the specimen, see JG / T283
- Q:What is the usual leveling of the ground? By which type of work to complete?
- The ground of the kitchen and the bathroom needs to be leveled, as it relates to the need for subsequent flattening tiles and slopes of water, which is done by the mason. If it is the floor, then it is involved in what you use the floor? If it is solid wood flooring that will use the wood keel, wood keel spacing is based on the length of the floor to set, the general spacing is one-third of the floor. This work is done by carpentry or people who sell the floor. Specifically who does it depends on you. Leveling the standard is actually looking for a horizontal line. If it is a composite floor, it depends on your room how the ground flatness. If the problem is not big, it can be laid directly on the ground, (solid wood flooring below is sure to play wooden keel), but under the floor of the moisture pad is certainly not less. If the flatness of the room is not enough, then it needs leveling, leveling the material can be "self-leveling." It is a kind of cement mortar like glue-like objects, poured on the ground will flow to the various corners of the room to make the role of the ground level, dry after the ground on the flat. There is also a way to play in the composite floor under the wooden keel leveling, after playing wood keel but also covered with blockboard. But this is more expensive than "self-leveling". Leveling the standard is actually looking for a horizontal line.
- Q:The use of lime mortar as the wall paint material, after a period of time, there have been protruding radial cracks, try to analyze the reasons
- The second is plastering, the mixing of the mortar is too thin, or plaster face close too early
- Q:In accordance with the instructions on the waterproofing agent package with a high proportion of sand but the decoration master said that is not very puzzled more
- Do a good job to fight forging toddler pedal Bang Quan burst water to use polyurethane and polypropylene you that is a high-grade cement, but one year will leak leh hh try it
1. Manufacturer Overview |
|
---|---|
Location | |
Year Established | |
Annual Output Value | |
Main Markets | |
Company Certifications |
2. Manufacturer Certificates |
|
---|---|
a) Certification Name | |
Range | |
Reference | |
Validity Period |
3. Manufacturer Capability |
|
---|---|
a)Trade Capacity | |
Nearest Port | |
Export Percentage | |
No.of Employees in Trade Department | |
Language Spoken: | |
b)Factory Information | |
Factory Size: | |
No. of Production Lines | |
Contract Manufacturing | |
Product Price Range |
Send your message to us
Support grouting material
- Loading Port:
- Qingdao
- Payment Terms:
- TT OR LC
- Min Order Qty:
- -
- Supply Capability:
- 2000吨 m.t./month
OKorder Service Pledge
OKorder Financial Service
Similar products
Hot products
Hot Searches
Related keywords