Harmonic Control and OVP Device (MRD-XHG)
- Loading Port:
- Tianjin
- Payment Terms:
- TT OR LC
- Min Order Qty:
- 1 unit
- Supply Capability:
- 30 unit/month
OKorder Service Pledge
OKorder Financial Service
You Might Also Like
Our complete device of arc & harmonic control and voltage protection is based on innovative theory, with full function and high automation. It could quickly eliminates electric arc, arc flash transient overvoltage, ferromagnetic resonace associated with ground fault by increasing current instantly to locat the ground line accurately, widely used in 3-35kv power grid in eletricity, metallurgy, chemical enterprises, coal mining, petroleum and industries like such. Main Functions 1.To replace PT cabinet and supply testing signal of voltage 2.With function of voltage protection, the device could limit atmosphere overvoltage and operating overvoltage at a lower level, so as to ensure insulation safty of power grid and electric equipment and reduce accidents casued by overvoltage a lot. 3. To replace arc-suppression coil, eliminate intermittent arc-grounding fault quickly, suppress intermittent arc-grounding overvoltage, prevent accidents from deteriorating and reduce accidental trip probability of wire. 4. To limit and eliminate various resonant overvoltage quickly and effectively, prevent aging-acceleration of system insulation structure caused by long time resonant overvoltage, avoid resonant overvoltage effection to power grid setting like arrester as well as small inductive load, increase safty & stability of system operation, and lengthen lifetime of system equipment. 5. To look up single-phase faulty wire accurately and quickly, prevent accident from deteriorating, reduce workload of operation and maintainance people. 6. The device possesses the function of switching TV. |
- Q: What is the GIS in power system
- Three Gorges Left Bank GIS a total of 39 switches. Left a total of 8 units of power station and the Three Gorges to Wanzhou 1 line, the Three Gorges to Longquan 1 lines, 2 lines, Three Gorges to Longquan Three Gorges to Longquan 3 lines of four circuits? Left two power plant a total of 6 units and the Three Gorges to Jingzhou 1 lines, 2 lines, Three Gorges to Jingzhou Three Gorges to Jingzhou 3 line etc. three lines.Three Gorges left bank power plant using international bidding procurement, GIS by the internationally renowned manufacturer ABB in 1999, the successful supply installation. The utility model relates to a metal sealed off phase structure, the generator transformer adopts a unit connection, and the two unit wiring is combined into a switch unit which is connected with a joint unit to connect the 3 / 2 wiring. Bus segment, 3 / 2 wiring of the 7 strings, a series of double switch off. GIS net size of about 581.5 meters long, width of 15 meters.
- Q: 1, what are the fire hazards caused by electricity in the server room?2 what are the fire hazards in the server room?
- Two, electrical fire monitoring system should be listed in the department or all the monitoring unit:1 electrical fire monitoring equipment;2 residual current type electric fire monitoring detector;3 temperature measuring electric fire monitoring detector;4 linear temperature fire detector
- Q: What are the characteristics of the grounding of the power system and equipment?
- Security grounding - is to protect the safety of the people and set the grounding point, such as: electrical equipment shell grounding, voltage transformer grounding two times, etc..
- Q: What is the LCP cabinet of electric power equipment
- Local control cabinetLocal control cabinet installed in the work site, which is likely to have PLC, the scope of the control cabinet than PLC wide
- Q: What are the necessary equipment for power line project?
- It must have a climbing tool, such as irons, safety belts, safety helmet; and lifting equipment, such as cranes, hydraulic lift truck, pulley, winch, pole and so on; there must be bearing equipment, such as various tensioners, hand gourd, line cards, traction machine, tension machine;
- Q: The company has a number of power equipment to be exported, need to go through the sea, the technical requirements of three, I would like to ask what is the three here? How to check whether the complete sets of components used to do three treatment? Please exhibitions, grateful!
- The complete set of power distribution equipment is a complete set of equipment supplied by the manufacturer. The electric main circuit is divided into a plurality of units, each unit is a circuit, and the circuit breaker, the knife gate, the current transformer and the voltage transformer of each unit are connected
- Q: Electric power equipment start-up and commissioning of the project there is a difference?
- The start of the equipment is started in the single test.
- Q: What is the meaning of the station control layer in the power system
- The process layer is an intelligent primary equipment in the exponential transformer substation, such as the intelligent terminal of the intelligent circuit breaker which is not yet fully developed, and the merging unit of the electronic transformer
- Q: The state of power system equipment is divided into four states
- (1) running state. The isolating switch and circuit breaker of the equipment are in the closing state, and the circuit is connected between the power supply and the receiving end.(2) hot standby. The circuit breaker of the equipment is disconnected, and the isolating switch is in the closing state. (3) cold standby. The circuit breakers and disconnecting switches of the equipment are in the open position.
- Q: Power equipment is required to replace the dimension, the state has no relevant provisions
- This depends on the provisions of the local power supply department, generally not mandatory requirements.
Send your message to us
Harmonic Control and OVP Device (MRD-XHG)
- Loading Port:
- Tianjin
- Payment Terms:
- TT OR LC
- Min Order Qty:
- 1 unit
- Supply Capability:
- 30 unit/month
OKorder Service Pledge
OKorder Financial Service
Similar products
Hot products
Hot Searches
Related keywords