• Bridge formwork system System 1
  • Bridge formwork system System 2
Bridge formwork system

Bridge formwork system

Ref Price:
get latest price
Loading Port:
China Main Port
Payment Terms:
TT OR LC
Min Order Qty:
-
Supply Capability:
-

Add to My Favorites

Follow us:


OKorder Service Pledge

Quality Product, Order Online Tracking, Timely Delivery

OKorder Financial Service

Credit Rating, Credit Services, Credit Purchasing

Building Bridge Formwork:

A compositional steel formwork system mainly used in the building which has regular structure

without beams, the excellent formwork system can make the integral pouring for the wall & slab

easily achieved.


Characteristics:

◆ No assembling, easy operation with formed formwork.

◆ High stiffness, make perfect shape for concrete.

◆ Repeatedly turnover is available.

◆ Widely applied range, such as building, bridge, tunnel, etc.



Q:The tunnel structure of plastic mould
The tunnel model is a kind of tool form template which is used for pouring concrete wall and floor at the same time.Total tunnel mode tunnel mode and half tunnel mode two, the basic unit of the tunnel mode is a complete tunnel template, half tunnel is composed of a plurality of unit angle die, and then use the 2.5 tunnel mode to fight and become a complete tunnel mode.
Q:I would like to ask the tunnel step method excavation, the height of each step is how to divide?
The side ditch construction using composite steel formwork. (1) the temporary facilities of tunnel construction plan layout: in the single ended due to tunnel entrance, temporary facilities of tunnel construction in tunnel exit to the right. The layout for the layout of wind mechanical equipment in the right side of the roadbed export based on the terrain conditions, reservoir located in the left side from the position of about 80m. In the mechanical approach immediately after the entrance of earth excavation construction, roof slope and drainage ditches slope anchor slope reinforcement, well hole digging for. (2): the excavation and reinforcement the mechanical construction, according to the construction method of Subgrade Earthwork excavation, dig to the rock when, in order to minimize the disturbance of the entrance slope and subgrade slope, must adopt the method of weak blasting and presplitting blasting for excavation. The entrance slope using hang net shotcrete reinforcement, to facilitate the safety hole (3). The excavation and support of the shallow section of the surrounding rock of the cave: the construction method adopts the step method, and the advanced grouting bolt is adopted on the stage
Q:The periphery of the tunnel outline has been sealed with steel seal, and can be used as the external formwork when the concrete is poured. The 3 parts of the tunnel are divided into floor, side wall and roof. When pouring, the concrete can only be pumped in the tunnel, the outside of the tunnel is the Pearl River, and the construction can not be carried out outside the tunnel. The roof pouring, only from the bottom to the pump. Question: 1, the roof concrete pouring, how to discharge the air? How to tamper? 2, the tunnel width of 23 meters, you need to do the construction of the seam or after pouring it? Time is pressing, please reply as soon as possible. Good addition score. Thank you。 If you can't see the picture, click this link:
The floor concrete is made by the method of subsection pouring, the length of each section is about 16 ~ 24m, and the construction joint is kept between each construction section. After pouring concrete floor, due to the need for roughly 7 days to meet the design requirements of concrete strength, to remove the floor above the first steel purlin and support. During this period of time can be the first construction of steel bars and formwork works, and then the construction of the outer wall of the leveling layer and the wall of the waterproof layer.
Q:Tunnel two lining car moving outside the template after the demolition of how the car is similar to the nature of the sliding movement and concrete off
No, the car is a mechanical structure, the first car on the template brush oil release agent or diesel oil, to prevent sticking
Q:How the arch of the tunnel concrete pouring up, how to support before pouring, using I-beam is directly support the earth?
The excavation of the tunnel face, slag, to the primary support system, first hit the bolt, then use steel or steel made of steel, installation support in tunnel contour, and then sprayed concrete (poor surrounding rock hanging steel mesh, then sprayed fiber concrete).
Q:Main diseases and prevention of tunnel
Tunnel shotcretePhenomenon: the concrete spray layer and the rock surface is not bonded, concrete spray layer between the bond is not good.Cause analysis: the loose rock not clear spray surface; shotcreted rock debris is not scum washing or flushing thoroughly with wind pressure, water pressure; surface by spraying water, water, water concentration of untreated concrete spraying interval; before a layer of spray surface without wind, water washing scum. The air pressure is inconsistent with the spray distance.Preventive measures: remove the loose rock, clear surface by spraying of water, slag floating debris; water, concentrated water point of the surface by spraying with gouge, guide the drainage treatment of buried pipe; sprayed concrete before spray test, to determine the wind and spray distance coordination relationship between.
Q:A detailed method is introduced
5) the construction of open cut tunnel reinforced concrete structure construction is divided into two parts: first, the construction of inverted arch and wall foundation of reinforced concrete, to be part of the concrete reaches certain strength, stripping, cutting hair construction joints, and construction of the upper side wall and arch of reinforced concrete. The inverted arch and wall part of the composite steel formwork, artificial pouring, side wall and arch concrete construction formwork for the internal mold, and molded with combined steel formwork, formwork and external bracing to ensure stable, symmetrical pouring concrete, steel processing plant in processing molding, binding site. The concrete is produced by the automatic metering concrete mixing station, the concrete transport vehicle transportation, the concrete pump into the mold, the insertion type tamping device is compacted, and the arch wall concrete is completed once.6) water proof construction, laying waterproof layer, tunnel construction on the surface of concrete repair chisel flat uneven place to prevent damage of waterproof board. The weld quality of the waterproof board shall meet the requirements. If there is any defect, corrective action must be taken to meet the requirements.7) arch backfilling: Myeongdong vault above maximum backfill height 2m, compaction degree '93% fill in the top-level clay layer of water, the backfill surface of turf.Back fill both sides of the symmetry at the same time, the bottom of the wall filled with 0.5m ~ 1m thick gravel and compacted, and then the use of artificial layered backfill, layer by layer compaction. Careful protection of the waterproof layer during backfilling is not destroyed.The water layer of clay and the side, the slope of the lap is good, close to prevent surface water leakage.
Q:Would you please tell me the difference between the concrete and shotcrete in the tunnel?
Characteristics of shotcrete:(1) the sprayed concrete has the characteristics of rapid growth, strong bonding force, high density and good impermeability. It can better fill the gap between the rock blocks, increase the integrity of the surrounding rock, prevent the free surface weathering and loosening, and work together with the surrounding rock.(2) the construction of shotcrete will transfer, pouring and tamping a few processes into one, and do not need a template, so the construction of fast, simple.(3) sprayed concrete can play an important role as early as possible.(4) compared with the concrete, the physical and mechanical properties of sprayed concrete are improved.
Q:How to put the positioning point is based on what is mainly based on my novice, do not
The next two large positioning along the side mode, re positioning of two small side mode along the point, then turn to check the center point and elevation, if not the positioning deviation is complete, then re adjust the positioning deviation! If you have time to measure the location of the site can be set up, then you do not nail this method, the five points directly to the elevation and mileage can be controlled for a long time
Q:Who can give me detailed tunnel construction process
On the inner side wall heading section is advanced, the footage was 0.7m immediately on the rock surface at the beginning of the spray, install the first layer of rock along Phi 8 steel mesh, and connected into a whole, set up active and temporary supporting steel arch, and the arch and a connected whole Phi 25 steel, drilling into the phi 25 hollow bolt and grouting, the installation of second layer steel mesh shotcrete layer to design contour line, pay attention to every compact trusses on the back of the footage, about 5~10m after the excavation under the heading section, and the lateral wall of drift can also present a ring section excavation footage was about 20 ~ 35m, support the arch excavation core soil upper arc heading, 3 ~ 5 after excavation footage and central support, under the section of tunnel bottom and the lower end of the previous about heading completely combined with closed loop, is divided into seven excavation, all operations must strictly follow the open Step by step, must be two inside the wall first, follow up the process step by step process. At the same time there must be monitoring data as the basis, redistribution of stress or conversion, will increase the support displacement, and strata subsidence and deformation, should strengthen the monitoring capacity before and after removal of the tunnel deformation and supporting force measurement,

1. Manufacturer Overview

Location
Year Established
Annual Output Value
Main Markets
Company Certifications

2. Manufacturer Certificates

a) Certification Name  
Range  
Reference  
Validity Period  

3. Manufacturer Capability

a)Trade Capacity  
Nearest Port
Export Percentage
No.of Employees in Trade Department
Language Spoken:
b)Factory Information  
Factory Size:
No. of Production Lines
Contract Manufacturing
Product Price Range

Send your message to us

This is not what you are looking for? Post Buying Request

Similar products

New products

Hot products


Hot Searches

Related keywords